How long does the job really take?
Ask most owners how long a job takes and you get a guess: about a day, maybe two guys for half a day. That guess drives the price, the schedule, and whether a crew had a good day. Writing down production rates turns the guess into a number you can trust.
What is a production rate?
It is how long a kind of work takes, per unit, with a given crew and equipment. How long to prune one palm of a certain height. How long to grind a stump of a certain size. How long to haul a load.
At Ptolemy, every price and every schedule reads from that page.
Why does it matter so much?
Because labor is usually the biggest cost in a service business, and it keeps rising. The U.S. Bureau of Labor Statistics puts the median wage for grounds maintenance workers at $19.27 an hour as of May 2025. A job you think takes four hours and really takes six loses money every time you sell it.
It is also a safety issue. BLS lists tree trimmers and pruners among the occupations with the highest rates of injuries and illnesses. A schedule built on wishful timing pushes crews to rush. Rushing is how people get hurt.
How do you set a production rate?
Three rules:
- Measure, do not remember. Time real jobs. A rate from memory is a guess with a decimal point.
- Say which kind of number it is. Measured, meaning somebody timed it. Recalled, meaning an honest account from experience. Or one person’s best day. They are not the same, and a recalled number never becomes measured just by being repeated.
- Update it when anything changes. New equipment, new crew, new site conditions, new rate.
What do you do with the rates?
- Price from them. Time times crew cost, plus equipment, materials and margin.
- Schedule from them. A day holds what the rates say it holds, not what you hope.
- Coach from them. If a crew runs well over the rate, find out why. If they run well under, find out what they know.
How to start
- Pick your three most common jobs.
- Time the next five of each. Write down crew size, equipment and conditions.
- Use the middle number as your rate, marked measured.
- Price your next quote from it.
Once your production rates are written down, pricing stops being an argument and scheduling stops being a hope.
Questions
What is a production rate?
How long a kind of work takes per unit, with a given crew and equipment. For example, minutes to prune one palm of a certain height.
How do you set production rates?
Time real jobs, record the crew and equipment, mark whether the number was measured or remembered, and update it when anything changes.