How long does the job really take?

Ask most owners how long a job takes and you get a guess: about a day, maybe two guys for half a day. That guess drives the price, the schedule, and whether a crew had a good day. Writing down production rates turns the guess into a number you can trust.

What is a production rate?

It is how long a kind of work takes, per unit, with a given crew and equipment. How long to prune one palm of a certain height. How long to grind a stump of a certain size. How long to haul a load.

At Ptolemy, every price and every schedule reads from that page.

Why does it matter so much?

Because labor is usually the biggest cost in a service business, and it keeps rising. The U.S. Bureau of Labor Statistics puts the median wage for grounds maintenance workers at $19.27 an hour as of May 2025. A job you think takes four hours and really takes six loses money every time you sell it.

It is also a safety issue. BLS lists tree trimmers and pruners among the occupations with the highest rates of injuries and illnesses. A schedule built on wishful timing pushes crews to rush. Rushing is how people get hurt.

How do you set a production rate?

Three rules:

  1. Measure, do not remember. Time real jobs. A rate from memory is a guess with a decimal point.
  2. Say which kind of number it is. Measured, meaning somebody timed it. Recalled, meaning an honest account from experience. Or one person’s best day. They are not the same, and a recalled number never becomes measured just by being repeated.
  3. Update it when anything changes. New equipment, new crew, new site conditions, new rate.

What do you do with the rates?

  • Price from them. Time times crew cost, plus equipment, materials and margin.
  • Schedule from them. A day holds what the rates say it holds, not what you hope.
  • Coach from them. If a crew runs well over the rate, find out why. If they run well under, find out what they know.

How to start

  1. Pick your three most common jobs.
  2. Time the next five of each. Write down crew size, equipment and conditions.
  3. Use the middle number as your rate, marked measured.
  4. Price your next quote from it.

Once your production rates are written down, pricing stops being an argument and scheduling stops being a hope.

Questions

What is a production rate?

How long a kind of work takes per unit, with a given crew and equipment. For example, minutes to prune one palm of a certain height.

How do you set production rates?

Time real jobs, record the crew and equipment, mark whether the number was measured or remembered, and update it when anything changes.